How to use it
- Pick a template: production schedule, trade fair or product launch.
- Change the start date, task names and durations; use starts at [task]'s end for dependencies.
- Download SVG or PNG for customers and colleagues; when a date slips, edit one line and the whole chart reflows.
Syntax cheat sheet
| Syntax | Meaning |
|---|---|
Project starts 2026-11-02 | Project start date |
| [Samples] lasts 10 days | A task and its duration |
| [Samples] starts at [Research]'s end | Starts when another task ends (dependency) |
| [Launch] happens at [Samples]'s end | A milestone (diamond) |
saturday are closed | Skip weekends |
2026-10-01 to 2026-10-07 are closed | Skip holidays |
| [Samples] is colored in LightBlue | Colour a task |
| [Samples] is 60% completed | Show progress |
language zh | Chinese dates and weekdays |
Frequently asked questions
Why not draw the Gantt chart in Excel?
In Excel, changing one duration means moving every later task by hand; here you state "starts when X ends", so later tasks shift automatically and weekends and holidays are skipped.
How do I skip weekends and holidays?
Write saturday are closed and sunday are closed for weekends, and 2026-10-01 to 2026-10-07 are closed for holidays. Durations then count working days.
Can it show progress and milestones?
Yes. [Task] is 60% completed shows progress, [Ships] happens at [Packing]'s end draws a diamond milestone, and [Task] is colored in LightBlue colours a task.
Is my plan stored or published?
No. For the preview the source is rendered on this site's server in sandbox mode and discarded at once; a share link keeps the source inside the link itself.